Which of the following methods allows construction to begin even if the design is not complete?

Guaranteed maximum price

Cost plus fixed fee

Fast track construction

Fast track construction is a project delivery method that enables construction activities to begin before the entire design is completed. This approach allows for overlapping of design and construction phases, which can significantly accelerate the overall project timeline. By utilizing this method, various construction components can be initiated as soon as the design for those specific elements is finalized, rather than waiting for the full set of plans to be complete. This can be particularly beneficial in circumstances where time is of the essence or where early completion can lead to substantial financial advantages.

In contrast, the other methods such as guaranteed maximum price, cost plus fixed fee, and design/bid/build typically rely on having most or all design details finalized before commencing construction. These methods do not support the same level of overlap between design and construction that fast track construction does, thus limiting the ability to start work before the entire design is completed.

Get further explanation with Examzify DeepDiveBeta

Design/bid/build

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy