Construction Management Practice Exam 2025 – The Comprehensive All-In-One Guide to Exam Success!

Question: 1 / 400

Should contractors expect additional payment for an excusable delay, such as one caused by harsh weather?

True

False

Only if specified in the contract

Contractors typically do have the opportunity to seek additional payment for excusable delays, such as those caused by harsh weather, as long as those delays are recognized in the contract or generally accepted under relevant construction laws. Excusable delays are unforeseen hindrances that are beyond the contractor's control and may justify an extension of time to complete the work without penalty, but they do not automatically entitle the contractor to extra compensation.

In many construction contracts, the provisions clarify how such delays are treated. For example, if the contract includes specific clauses that outline compensation for excusable delays, then the contractor may indeed be entitled to additional payment. If the contract lacks such language, or if the delay does not impact the cost or schedule in a way that the contract anticipates, then the contractor may not be compensated for the delay.

In general, various types of delays are classified into categories—excusable, inexcusable, and compensable—so understanding the nature of the delay is crucial. If the delay falls into a category that the contract specifies allows for compensation, then contractors can expect payment. The view that contractors do not have a right to expect additional payment without explicit contractual grounds emphasizes the importance of the specific terms outlined in their agreements with project owners.

Ask an Examzify Tutor

Depends on the type of delay

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy