Which of the following is an example of an excusable delay?

Delay caused by subcontractor

Delay due to material shortage

Delay due to inclement weather

An excusable delay is one that is beyond the control of the contractor and is typically recognized in construction contracts as a legitimate reason for a delay in project completion without penalty. This type of delay usually has provisions that allow the contractor to seek an extension of time.

Inclement weather fits this definition well because it is often unpredictable and cannot be anticipated. Extreme weather conditions, such as heavy rain, snow, or hurricanes, can halt construction activities and are generally accepted in the industry as valid reasons for delaying project timelines. Contracts often include clauses that specifically address weather-related delays, detailing how they can affect the construction schedule.

In contrast, delays caused by subcontractors, material shortages, or miscommunications are generally not considered excusable delays. These delays are usually within the control of the contractor to manage and plan around, making them more challenging to justify as legitimate reasons for extending project completion dates.

Get further explanation with Examzify DeepDiveBeta

Delay from miscommunications

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy